Four men dig a ditch in 42 days but one works half-days. The job takes:
Four men dig a ditch in 42 days but one works half-days. The job takes:
Answer: "48 days"
With one man working half-days four men’s effective workforce extends the 42-day ditch-digging task to 48 days. This work-rate calculation is key for project planning and resource management.